Vendor shipment ETA slipped from W22 to W24. 9-day delay against float of 3 days.
Impact: May defer steel erection start by ~2 weeks, cascading into Pkg 4 tie-in windows.
4 open NCRs against Al-Rashid, avg age 3.7 days. Historical closure rate falling below SLA.
Impact: Hydro-test window for Loop HT-04-11 at risk; adds 5–7 days to commissioning path.
Weld traceability for 12 P22 header welds not fully closed. Aramco QA audit scheduled W23.
Impact: Potential re-inspection; ~$180k rework exposure and 4-day float loss.
Primavera P6 sync: 3 activities behind baseline on Pkg 4 critical path.
6 min agoSAP PS sync: Package 4 cost variance detected — –1.4% vs baseline.
10 min agoANCHOR AI flagged NCR-2847 as overdue (>48 hrs) — draft escalation prepared for review.
12 min agoRFQ comparison for Vendor Package 4 (Utility Piping) completed — 6 bidders analysed.
1 hr agoFlash Report — Day 142 generated. Ready to send to PMT.
3 hr agoRisk RSK-041 escalated from Medium to High based on updated LLI tracker.
5 hr agoNCR-2870 (grouting voids) closed by Al-Jazeera Civil Works after re-work verification.
YesterdayANCHOR AI detected PMI mismatch on spool 5-P-2201 — NCR-2884 auto-drafted for QC approval.